Non-Refund of Differential 6% GST Liability Borne by Contractors for Works Contracts: Chhattisgarh HC directs Refund of Excess Tax Paid within 4 Months [Read Order]
The petitioners contended that their bids were based on the prevailing 12% GST rate, and the retrospective application of the higher rate without a refund mechanism was unjust
By Manu Sharma - On April 20, 2024 4:15 pm - 2 mins read
The Single Bench of Justice Rajani Dubey of the High Court of Chhattisgarh directed the department to refund the excess Goods and Services Tax paid by the contractors at the rate of 18% on Works Contracts. The petitioners contested against the imposition of an 18% GST rate on contracts executed before 18.07.2022 and sought a…
Your free access to Taxscan has Expired
To read the article, get a premium account.
Taxscan Premium
Why should you subscribe?
Enjoy our website without interruptions from advertisements
Receive Daily newsletters
Receive realtime Telegram/Whatsapp news updates
Download original Judgements / Order / Notifications / Circulars, etc